Reports submitted to the Floodplain Risk Management Advisory Committee to be held on Thursday 2 July 2026.

Agenda
and
Business Paper
Floodplain Risk Management Advisory Committee
To be held on
Thursday
2 July 2026
at 8:30 AM
Civic Centre cnr Baylis and Morrow Streets,
Wagga Wagga NSW 2650 (PO Box 20)
P 1300 292 442
P council@wagga.nsw.gov.au
wagga.nsw.gov.au
Floodplain Risk Management Advisory Committee AGENDA AND BUSINESS PAPER
Thursday 2 July 2026
ORDER OF BUSINESS:
CLAUSE PRECIS PAGE
ACKNOWLEDGEMENT OF COUNTRY 2
APOLOGIES 2
Confirmation of Minutes
CM-1 CONFIRMATION OF MINUTES - FLOODPLAIN RISK MANAGEMENT ADVISORY COMMITTEE - 14 APRIL 2026 2
DECLARATIONS OF INTEREST 2
Reports from Staff
RP-1 2021-22-FM-0032 - Uranquinty Levee Upgrade - Investigation and Design 3
RP-2 2022-FMP-0103 Humula and Mangoplah Flood Studies 5
RP-3 17866- Levee System Upgrade - North Wagga 7
RP-4 WWCC MOFFs FFL Amendment review 9
RP-5 Flood Project Implementation Status 11
QUESTIONS WITH NOTICE 13
Wagga Wagga City Council acknowledges the traditional custodians of the land, the Wiradjuri people, and pays respect to Elders past, present and future and extends our respect to all First Nations Peoples in Wagga Wagga.
We recognise and respect their cultural heritage, beliefs and continuing connection with the land and rivers. We also recognise the resilience, strength and pride of the Wiradjuri and First Nations communities.
CM-1 CONFIRMATION OF MINUTES - FLOODPLAIN RISK MANAGEMENT ADVISORY COMMITTEE - 14 APRIL 2026
That the Minutes of the proceedings of the Floodplain Risk Management Advisory Committee Meeting held on 14 April 2026 be confirmed as a true and accurate record, noting Council’s adoption of these minutes at its meeting of 11 May 2026
|
1⇩. |
FRMAC Minutes - 14 April 2026 |
14 |
|
Report submitted to the Floodplain Risk Management Advisory Committee on Thursday 2 July 2026 |
RP-1 |
Reports from Staff
RP-1 2021-22-FM-0032 - Uranquinty Levee Upgrade - Investigation and Design
Author: Andrew Mason
|
Summary: |
The project for the design of the levee upgrade has been completed. |
|
That the Floodplain Risk Management Advisory Committee receive and note the update provided in relation to the Uranquinty Levee Upgrade Project. |
Report
The levee design and all of the associated reports are complete and being provided to Council as Haskoning sign them off for distribution.
The deliverables include:
· IFC Design drawings
· Levee Design Report
· Utility Investigation Report
· Review Of Environmental Factors
· Levee Owners Manual
· Construction Methodology Report
· Safety By Design Report
· Specification Development
· Schedule of Quantities
Aboriginal Land Claim
The NSW Aboriginal Land Council has recently issued a claim over Crown land across many areas of the LGA. These claims include blocks of land that contain both the existing and potential future levee alignment. As per our current practice in this situation, Council will approach the Land Council to negotiate a solution for these parcels of land which will involve the removal of the relevant parcels from the claim or Council acquire an easement over the parcel for drainage, flood and maintenance purposes.
Disaster Ready Fund Round 4
Council has chosen to apply for funding for the rebuild and upgrade of Glenfield Drain for this round of DRF funding. The most significant reason for not going with Uranquinty was the uncertainty around the Land Claims and access to the Crown Land for the levee extension on the Eastern side of Uranquinty. Council staff will work with Crown Lands and the Land Council over the next twelve months to resolve the land issues and the probable intention is to apply for funding for the levee upgrade through the next round of DRF funding in 2027.
Financial Implications
N/A
Policy and Legislation
N/A
Link to Strategic Plan
Regional Leadership
Ethical Leadership
Provide strategic direction and leadership for our region to deliver key community priorities.
Risk Management Issues for Council
N/A
Internal / External Consultation
N/AN/A
|
Report submitted to the Floodplain Risk Management Advisory Committee on Thursday 2 July 2026 |
RP-2 |
RP-2 2022-FMP-0103 Humula and Mangoplah Flood Studies
Author: Andrew Mason
|
Summary: |
WMAWater have completed the modelling and reporting for the flood model for the study for Humula and Mangoplah and are seeking endorsement to place the model and report on Public Exhibition . |
|
That the Floodplain Risk Management Advisory Committee receive and note the update provided in relation to the Humula and Mangoplah Flood Studies Project and endorse the model and report to go on Public Exhibition |
Report
Council engaged WMAWater in late September 2023, to undertake the Humula and Mangoplah Flood Study.
WMAWater have been preparing the reporting for the Mangoplah and Humula Flood Study. In preparing the report, it was identified that some additional model simulations were required. These have been progressed, and the Draft Flood Study report has been provided to Council. Council and DCEEW provided feedback to WMA Water about the model and report and this feedback has been incorporated into a draft final report.
WMA Water has finalised the update of the Flood Study and the report and modelling is going to be presented to Council at a workshop on the 20th July prior to going on Public Exhibition for 28 days.
A time extension until September 2026 has been approved by DCCEEW for this project. This allows time for Public Exhibition, FRMAC meetings and Council meetings.
Financial Implications
N/A
Policy and Legislation
N/A
Link to Strategic Plan
Regional Leadership
Ethical Leadership
Provide strategic direction and leadership for our region to deliver key community priorities.
Risk Management Issues for Council
N/A
Internal / External Consultation
N/A
|
Report submitted to the Floodplain Risk Management Advisory Committee on Thursday 2 July 2026 |
RP-3 |
RP-3 17866- Levee System Upgrade - North Wagga
Author: Andrew Mason
|
Summary: |
The project to upgrade the North Wagga levee has commenced with preliminary tasks completed and with some grant funding closures becoming due. |
|
That the Floodplain Risk Management Advisory Committee receive and note the update to the Levee System Upgrade – North Wagga. |
Report
A new project specifically about the implementation of the levee raising and third-party mitigation options has commenced.
An updated indicative timeline for the implementation of the raised levee and third-party mitigation options is provided below.
|
Stage |
Duration |
Commencement |
Status |
|
Topographic Survey |
6 months |
August 2024 |
Complete |
|
Environmental Assessment |
4 months |
November 2024 |
Complete |
|
Floodgate Pipe Relining |
4 months |
September 2025 |
Complete
|
|
Civil Design including mitigation options for residents adversely affected by the levee raising |
6-12 months |
December 2025 |
PWA NSW are the design consultant. Council will be negotiating with affected landholders |
|
Levee contractor procurement |
4 months |
December 2026 |
Not due |
|
Levee construction |
24 months |
November 2027 |
Not due |
For the North Wagga levee, Council currently has a funding pool of:
· $6.1M in SRV funding
· $1.1M in the original Commonwealth Development Grant (CDG) to be expended by 30 June 2026.
· $9.1M in DRF round three funding
The CDG has been allocated to fund the floodgate pipe relining, the detailed design of the levee, purchase of sheetpiles and the purchase of 5 floodgates.
The status of the project is:
· The detailed survey for the levee design has been completed.
· The Review of Environmental Factors has been completed and accepted by Council
· The detailed design of the levee has been awarded to NSWPW after negotiations with GHD failed to reach a successful conclusion.
· Pipeline Watertech have completed the relining of the existing 11 floodgates in the levee, the remaining three floodgates require significant levee work as well as the relining and this will be undertaken as a component of the levee rebuild.
· A project team has been engaged to oversee this complex project.
· NSWPW have completed a site visit and commenced work on the revised design
· All residents on the floodplain outside the levee adversely affected by the levee raising have been consulted and detailed survey information from their properties has been obtained.
Financial Implications
N/A
Policy and Legislation
Local Government Act
Development Control Plan 2010
Flood Risk Management Manual
Link to Strategic Plan
Regional Leadership
Ethical Leadership
Provide strategic direction and leadership for our region to deliver key community priorities.
Risk Management Issues for Council
N/A
Internal / External Consultation
|
Report submitted to the Floodplain Risk Management Advisory Committee on Thursday 2 July 2026 |
RP-4 |
RP-4 WWCC MOFFs FFL Amendment review
Author: Sam Robins
Director: Julie Costa
|
Summary: |
Council has engaged GLN Planning and WMS Engineering to review the Flood Planning Area and the Finish Floor Level (FFL) in the MOFFs Study and Plan.
|
|
That the Floodplain Risk Management Advisory Committee receive and note that a detailed report is being prepared with the intent that it will be available for consideration at Septembers meeting. |
Report
Background
A briefing of the intent of the report was presented at the April meeting with the aim that a report would be available for July’s meeting. This deadline has not been achieved and has been pushed back to September. It is not expected that there will be any issues with meeting this revised deadline.
Next Steps
Council staff to engage with consultants over the next two months and prepare a report for the September meeting.
Financial Implications
Council funding from internal budget.
Policy and Legislation
Environmental Planning and Assessment Act 1979
Local Government Act 1993
Link to Strategic Plan
Regional Leadership
Ethical Leadership
Provide strategic direction and leadership for our region to deliver key community priorities.
Risk Management Issues for Council
Ensure any recommendation remains consistent with the NSW Flood Risk Management Manual and therefore provide Council the protection it requires under section 733 of the Local Government Act 1993.
Internal / External Consultation
N/A
|
Report submitted to the Floodplain Risk Management Advisory Committee on Thursday 2 July 2026 |
RP-5 |
RP-5 Flood Project Implementation Status
Author: Andrew Mason
|
Summary: |
This Report outlines the status of the flood projects across the various studies that Council currently has underway. |
|
That the Floodplain Risk Management Advisory Committee receive and note the report in relation to Flood Project Implementation Status. |
Report
Council has over 80 recommendations from the recently completed studies and is working its way through the studies.
The spreadsheet tracking these projects is an attachment in the committee Shared Space.
Financial Implications
N/A
Policy and Legislation
N/A
Link to Strategic Plan
Safe and Healthy Community
Objective: Our community feel safe
Be responsive to emergencies
Risk Management Issues for Council
As outlined in the Report.
Internal / External Consultation
N/A
Reports submitted to the Floodplain Risk Management Advisory Committee to be held on Thursday 2 July 2026.
QUESTIONS WITH NOTICE